Monthly site report · November 2026

Construction progress

EJR and Al Muzn Developments build these projects together. Every month we visit the sites and report here, in plain words, how far each building has got.

Marasi Saada 1
Artist’s impression

Marasi Saada 1

Finishing works now run on every floor, and the show apartment on the first floor has its final finishes.

Progress reported to
19 November 2026
Planned handover
May 2027
The front facade after priming, November 2026
An apartment on the first floor, November 2026
Bathroom tiling on the second floor, November 2026
Third-floor corridor ceiling, November 2026
  1. Excavation
  2. Foundations
  3. Below ground
  4. Structure
  5. Walls
  6. Services
  7. Finishes
  8. Handover

On site this month

Ground floor and mezzanine
Plastering complete on the ground floor; a private entrance built for the mezzanine, where electrical work has started.
Floors 1 and 2
Painting and ceilings complete on floor 1; floor and bathroom tiling well advanced on both floors; floor 2 ceilings nearly complete.
Floors 3 to 5
Ceilings in progress on floor 3; electrical and plumbing work continues; walls being prepared for paint on floor 5; floors 4 and 5 being prepared for floor tiling.
Facades
Front facade plastered and primed; side facade plastered; rear facade plastering in progress.

Next on the programme

  • Finish floor and bathroom tiling on floors 1 and 2
  • Start floor tiling on floors 4 and 5
  • Finish plastering the rear facade

Site progress reported by the main contractor and reviewed by EJR. The overall percentage is an indicative developer estimate.

Prices and available units →

All reports

Al Muzn Square
Artist’s impression

Al Muzn Square

Below-ground work is well advanced on the first blocks; the remaining blocks have broken ground.

Progress reported to
31 October 2026
Planned handover
December 2027
Ground-floor base preparation, October 2026
Concrete pouring on site, October 2026
Completed ground beam works, October 2026
Earthworks in progress, October 2026
  1. Excavation
  2. Foundations
  3. Below ground
  4. Structure
  5. Walls
  6. Services
  7. Finishes
  8. Handover

On site this month

Blocks A, B, C
Ground beams cast; backfill and the base for the ground-floor slab in progress.
Blocks G, H
Ground beams in progress.
Block I
Steel fixing for the ground beams has begun.
Blocks D, E, F
Excavation has begun.

Next on the programme

  • Ground-floor columns on Blocks A, B and C
  • Finish the ground beams on Block I
  • Carry on excavating Blocks D, E and F

Site progress reported by the main contractor and reviewed by Al Muzn Developments. The overall percentage is an indicative developer estimate.

Prices and available units →

All reports

Marasi Saada 2
Artist’s impression

Marasi Saada 2

Ground is broken: excavation is under way, with foundations to follow.

Progress reported to
Work started on site in October 2026
Planned handover
July 2029
  1. Excavation
  2. Foundations
  3. Below ground
  4. Structure
  5. Walls
  6. Services
  7. Finishes
  8. Handover

On site this month

Whole site
Excavation.

Next on the programme

  • Foundations

Prices and available units →

Page updated 19 November 2026. Each project shows the date its progress is reported to. Photos are real site photographs from the report of that month; the building images at the top of each project are artist’s impressions. Reports are published monthly.