Monthly site report · November 2026
Construction progress
EJR and Al Muzn Developments build these projects together. Every month we visit the sites and report here, in plain words, how far each building has got.

Marasi Saada 1
Finishing works now run on every floor, and the show apartment on the first floor has its final finishes.
- Progress reported to
- 19 November 2026
- Planned handover
- May 2027
- Excavation
- Foundations
- Below ground
- Structure
- Walls
- Services
- Finishes
- Handover
On site this month
- Ground floor and mezzanine
- Plastering complete on the ground floor; a private entrance built for the mezzanine, where electrical work has started.
- Floors 1 and 2
- Painting and ceilings complete on floor 1; floor and bathroom tiling well advanced on both floors; floor 2 ceilings nearly complete.
- Floors 3 to 5
- Ceilings in progress on floor 3; electrical and plumbing work continues; walls being prepared for paint on floor 5; floors 4 and 5 being prepared for floor tiling.
- Facades
- Front facade plastered and primed; side facade plastered; rear facade plastering in progress.
Next on the programme
- Finish floor and bathroom tiling on floors 1 and 2
- Start floor tiling on floors 4 and 5
- Finish plastering the rear facade
Site progress reported by the main contractor and reviewed by EJR. The overall percentage is an indicative developer estimate.
All reports
- November 2026 · progress to 19 November 2026 · 76%PDF (English)PDF (Arabic)
- October 2026 · progress to 18 October 2026 · 72%PDF (English)PDF (Arabic)

Al Muzn Square
Below-ground work is well advanced on the first blocks; the remaining blocks have broken ground.
- Progress reported to
- 31 October 2026
- Planned handover
- December 2027
- Excavation
- Foundations
- Below ground
- Structure
- Walls
- Services
- Finishes
- Handover
On site this month
- Blocks A, B, C
- Ground beams cast; backfill and the base for the ground-floor slab in progress.
- Blocks G, H
- Ground beams in progress.
- Block I
- Steel fixing for the ground beams has begun.
- Blocks D, E, F
- Excavation has begun.
Next on the programme
- Ground-floor columns on Blocks A, B and C
- Finish the ground beams on Block I
- Carry on excavating Blocks D, E and F
Site progress reported by the main contractor and reviewed by Al Muzn Developments. The overall percentage is an indicative developer estimate.
All reports
- Issue 02 · October 2026 · progress to 31 October 2026 · 30%PDF (English)PDF (Arabic)
- Issue 01 · September 2026 · progress to 30 September 2026 · 25%PDF (English)PDF (Arabic)

Marasi Saada 2
Ground is broken: excavation is under way, with foundations to follow.
- Progress reported to
- Work started on site in October 2026
- Planned handover
- July 2029
- Excavation
- Foundations
- Below ground
- Structure
- Walls
- Services
- Finishes
- Handover
On site this month
- Whole site
- Excavation.
Page updated 19 November 2026. Each project shows the date its progress is reported to. Photos are real site photographs from the report of that month; the building images at the top of each project are artist’s impressions. Reports are published monthly.